The house is still on schedule and possibly ahead of schedule. The siding looks real good and is complete on the north side of the house. You can see that the mason is working on the fireplaces.
The fireplace in the living room is roughed in and the roof should be finished around the chimney area so the shingles can be finished. It sure looks tall. Looking forward to seeing it with the finish stone on it.
The fluid for the geothermal system has been delivered, (Big plastic container), and the lines have been filled and connected to the furnaces.
The plumbing and the heating ducts have been started. There is a lot of both to do. (Notice the metal plates in front of the water lines and drains so that nails won't go into them when drywall is put up.)